Most of 74-343 study materials for your Microsoft 74-343 Managing Projects with Microsoft Project 2013 is exclusively prepared by the best brains and highly skilled professionals from the IT domain to ensure 100% pass percentage in your Microsoft 74-343 Exam. Easiest way to get Microsoft Project 74-343 test is to log on to the Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide Killtest and choose the 74-343 Test to do Microsoft 74-343 Online to obtain your 74-343 exam Microsoft Project certification. With Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide, you can be rest assured that you will be fully prepared to take on your Microsoft certification 74-343 Exam. The Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide are written by the great professionals who are specialist in studies. Killtest 74-343 study guides help you to ready for the real exam questions. These 74-343 study guides are prepared by Microsoft Certification who have had years of experience and are fully competent to give you the best and the most excellent way to prepare for your actual exam.

Microsoft Project 74-343 Practice Exam | Killtest Microsoft 74-343 Test Questions | 2017 New 74-343 Study Materials

You are a project manager who uses Project Professional 2013.You work on a software development project, and the Project Management Office (PMO) requires you to enter project costs associated with all work completed on your project.You receive invoices for $5,000 for software licenses and $150 for supplies.Software licensing costs are associated with Task A: Obtain Software License.Supply costs are associated with Task H: Project Management Administration.You need to enter the costs into your project schedule.Which two steps should you perform? (Each correct answer presents part of the solution.Choose two.)
A.Create a material resource for Supplies and Software License.
B.Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A, and enter the actual costs using the Task Usage – Cost table for both Task H and A.
C.Assign the Supply material resource to Task H, assign the Software License material resource to Task A, and enter the actual costs using the Task Usage – Cost table for both Task H and A.
D.Create a cost resource for Supplies and Software License.
Answer: DB

You are a project manager, and your organization uses Project Professional 2013.You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.What should you do?
A.Right-click the resource and reassign it to the underallocated resource.
B.Drag the underallocated resource on the task to reassign it.
C.Right-click the task and reassign it to the underallocated resource.
D.Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
Answer: C

You are a project manager for a company that uses Project Professional 2013.You are developing a schedule and plan to use the leveling order of Priority, Standard.You need to create a task which leveling will not change.What should you do?
A.Set task priority to 1000.
B.Set task priority to 0.
C.Set task priority to 100.
D.Set task priority to 1.
Answer: A

You are a project manager who uses Project Professional 2013.When viewing the critical path, you notice that there are some inconsistencies.To investigate the status of the critical path, you insert the Total Slack column into a task table.You discover that many of the tasks have negative Total Slack values.
You need to resolve the negative Total Slack values.What should you do?
A.Re-assign resources that have more availability at the time of the negative slack.
B.Remove lag time from task relationships.
C.Remove as many constraints as possible.
D.Remove lead time from the task relationships.
Answer: C

You are a project manager who uses Project Standard 2013.Your manager wants you to plan an office move.You have a project schedule from a prior office move named OfficeMove.mpp and you want to use this project to assist in planning the current office move.In the fewest steps possible, you need to create your new project schedule based on the old project schedule.What should you do?
A.Open the old OfficeMove.mpp file, click on Save As, and save the file using a new file name.Then enter the project name in the Project Summary Task.Set all tasks to zero percent complete.
B.Open the old OfficeMove.mpp file, change the project start date and project title, and clear the baseline.Save the file using the current project name.
C.Open the old OfficeMove.mpp file, save the file as an .mpt file type, removing the baseline and actual values.Save the .mpt file as an .mpp file type, assigning the current project name.
D.Open the old OfficeMove.mpp file, click on Save As, save the file using a new file name, clear the baseline, and set all tasks to zero percent complete.
Answer: C

Microsoft 74-343 exam is the most important, prominent and well known assessment test to check candidate’s ability for qualifying its certification. With the growing competition, it seems that it isn’t a simple thing to comprehend your fantasy. There are many test questions and study materials for you to choose when preparing the Microsoft 74-343 exam. But not every study guide is suitable for you. Killtest supplies using a lot of Microsoft Killtest for many individuals coming from beginners levels towards superior levels. No matter if you’re a prosperous specialized or possibly a beginner inside your picked job journey planning to include much more in your real exam, Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide seek to provide the very best already in the market. Seek Microsoft certification 74-343 practice exam from Killtest online 74-343 study materials and 74-343 test questions along with up to date 74-343 practice questions and answers to help you to cross your current Microsoft 74-343 Managing Projects with Microsoft Project 2013 certification exam.

Killtest is a very good website to provide a convenient service for the Microsoft 74-343 exam. Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide can help people whose IT knowledge is not comprehensive pass the difficulty Microsoft 74-343 exam. If you add the 74-343 practice exam of Killtest to your cart, you will save a lot of time and effort. The purpose of Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide are to promote Microsoft Certification 74-343 exam. At Killtest, 74-343 test questions will brief all the important 74-343 exam questions and 74-343 confirmed answers that is very much same as real Microsoft 74-343 exam. At Killtest, Microsoft Certification 74-343 practice exam for 74-343 Managing Projects with Microsoft Project 2013 exam will enhance your skill as well as the hidden learning abilities. If you choose Killtest Microsoft Project 74-343 Exam Microsoft 74-343 Study Guide, you can save a lot of time and energy to consolidate knowledge, but can easily pass Microsoft 74-343 exam.

Ad Reference ID: N/A

Leave a Reply

You must be logged in to post a comment.